PSE&G has announced the schedule for Gas Main Replacement work on the below listed streets for next week:
Week of 8/25/2025 (GAS MAIN WORK)
Mon. 8/25 to Tues. 8/26: Second Street (Lilac to Magnolia)
Wed. 8/27 to Thurs. 8/28: Magnolia Lane (Second to Fenimore)
Fri. 8/29: No Work Scheduled
Week of 8/25/2025 (SERVICE & TIE-INS)
Mon 8/25: Burlington Avenue (Walter to Rancocas)
Tues. 8/26 to Wed. 8/27: Vine Street (Delaware to Burlington)
Thurs. 8/28: Pennsylvania/Union & Union/Burlington - Tie-ins
Fri. 8/29: No Work Scheduled
Week of 9/01/2025 (GAS MAIN WORK)
Mon. 9/1: LABOR DAY - No Work Scheduled
Tues. 9/2 to Thurs. 9/4: Union Ave (Burlington to Pennsylvania)
Fri. 9/5: No Work Scheduled
Week of 9/01/2025 (SERVICE WORK)
Mon. 9/1: LABOR DAY - No Work Scheduled
Tues. 9/2 to Thurs. 9/4: Vine Street (Delaware to Burlington)
Fri. 9/5: No Work Scheduled
Please note this schedule is subject to change as conditions may warrant.